Etemadian M, Mosadeghrad A M, Mohaghegh Dolatabadi M R, Dehnavi H. The challenges of public-private partnership in hospital construction A case study. jhosp 2020; 19 (1) :19-32
URL: http://jhosp.tums.ac.ir/article-1-6147-en.html
1- Associate Professor, Urology department, Hasheminejad Kidney Center, Hospital Management Research Center, Iran University of Medical Sciences (IUMS), Tehran, Iran
2- Associate Professor, School of public health, Health information management research centre, Tehran University of Medical Sciences, Tehran, Iran.
3- Assistant Professor, Anesthesiology department, Hasheminejad Kidney Center, Hospital Management Research Center, Iran University of Medical Sciences (IUMS), Tehran, Iran
4- M.Sc.in health management, School of public health, Tehran University of Medical Sciences, Tehran, Iran, (*Corresponding author), Email: Hamedehnavi@gmail.com
Abstract:   (3664 Views)

Background: Public-private partnership (PPP) in constructing and operating hospitals is a good strategy to provide high quality services to people at lower cost for the government.  However, PPP is facing several challenges. The objective of this research was to identify and explore the PPP challenges in building Moheb Yas hospital in Tehran, Iran.
Materials and Methods: A qualitative approach was used for this case study in 2018. In-depth semi-structured interviews were conducted with 24 key stakeholders, managers and employees who were involved in PPP initiative implementation using purposive and snowball sampling methods. Thematic analysis approach was used for data analysis.  
Results: Moheb Yas hospital was built in the yard of a public hospital (Co-location PPP) by the private entity. Then, the public hospital was moved into the private hospital. The new hospital was transferred to the government after one year owing to some challenges. These challenges include an inappropriate PPP model, low government capacity and competency in PPP, low trust in private partner, difficulty in funding the project, demolishing the old building, applying for hospital licences, merging two public and private hospitals, and difficulties in equipping the new hospital with human and physical resources.
Conclusion: The PPP was not successful in this case. Although PPP initiatives have benefits for the health system, but, it comes with numerous challenges especially in developing countries owing to disparate goals, incentives, and management practices of public and private sectors. The research findings provide useful insights for policy makers and senior managers in health systems in similar countries about the main barriers of PPP initiatives in the health sectors.

Full-Text [PDF 975 kb]   (1985 Downloads)    
Type of Study: Original Article | Subject: مدیریت تسهیلات (فیزیکی ، تاسیساتی و تجهیزاتی ) در بیمارستان
Received: 2019/03/31 | Accepted: 2020/05/21 | Published: 2020/06/6

Add your comments about this article : Your username or Email:
CAPTCHA

Rights and permissions
Creative Commons License This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.

© 2024 , Tehran University of Medical Sciences, CC BY-NC 4.0

Designed & Developed by : Yektaweb